10.1 | Agreement between Gaylord National, LLC and Perini/Tompkins Joint Venture, dated as of May 9, 2005, relating to the construction of the Gaylord National, including certain amendments thereto (incorporated by reference to Exhibit 10.14 to the Companys Annual Report on Form 10-K for the year ended December 31, 2005, Exhibit 10.2 to the Companys Current Report on Form 8-K dated July 5, 2006, Exhibit 10.2 to the Companys Current Report on Form 8-K dated October 31, 2006, Exhibits 10.2, 10.3 and 10.4 to the Companys Current Report on Form 8-K dated April 18, 2007 and Exhibit 10.2 to the Companys Current Report on Form 8-K dated May 11, 2007 (File No. 1-13079)). | ||
10.2 | GMP Amendment No. 15 to the Agreement between Gaylord National, LLC and Perini/Tompkins Joint Venture, dated June 25, 2007. |
GAYLORD ENTERTAINMENT COMPANY | ||||||
Date:
June 26, 2007
|
By: Name: |
/s/ Carter R. Todd
|
||||
Title: | Senior Vice President, General Counsel and Secretary |
EXHIBIT | ||
NUMBER | DESCRIPTION | |
10.1
|
Agreement between Gaylord National, LLC and Perini/Tompkins Joint Venture, dated as of May 9, 2005, relating to the construction of the Gaylord National, including certain amendments thereto (incorporated by reference to Exhibit 10.14 to the Companys Annual Report on Form 10-K for the year ended December 31, 2005, Exhibit 10.2 to the Companys Current Report on Form 8-K dated July 5, 2006, Exhibit 10.2 to the Companys Current Report on Form 8-K dated October 31, 2006, Exhibits 10.2, 10.3 and 10.4 to the Companys Current Report on Form 8-K dated April 18, 2007 and Exhibit 10.2 to the Companys Current Report on Form 8-K dated May 11, 2007 (File No. 1-13079)). | |
10.2
|
GMP Amendment No. 15 to the Agreement between Gaylord National, LLC and Perini/Tompkins Joint Venture, dated June 25, 2007. | |
1. | Pursuant to the Agreement, Construction Manager hereby agrees that the Guaranteed Maximum Price (GMP) for the Work to be performed on the Project (including all Work under this GMP Amendment Number 15 and all Work previously authorized pursuant to GMP Amendments shall be $677,316,191 and that the GMP is accounted as follows: (a) the Preconstruction Services equals $350,000, (b) the Construction Managers Lump Sum General Conditions equals $24,459,680, (c) the Cost of the Work equals $615,767,045, (d) the Construction Managers Fee equals $20,549,963 (e) Contingency equals $15,938,947, (f) the Mock-up Room Cost of Work equals $250,557.) |
OWNER | CONSTRUCTION MANAGER |
|
GAYLORD NATIONAL, LLC | PERINI TOMPKINS JOINT VENTURE |
|
By: Gaylord Hotels, Inc. sole member |
By: |
/s/ David C. Kloeppel
|
By: | /s/ Mark Makary
|
|||
Title: |
EVP
|
Title: | Principal in Charge
|